Quote:
Originally Posted by doc_gonzo64
i'm one of 4 that runs the power house at a hardwood flooring plant. we run a boiler, use process steam for drying kilns and supper heated steam to run a turbine to produce electricity for the plant. we work a "dupont schedule" 12 hr shifts, 4 nights, 3 off, 3 days, 1 off, 3 nights, 3 off, 4 days, then a week off. i love the nights the most but i really love the week off every month.
doc
|
We do, 4 days on then 4 off. It makes for 12 day vacations,I like that part. I also will fit in a 2-6 hr. Nap tonight.